Scope of the work

- Prefabrication and installation of piping systems
(36.2 km – average diameter of 2 inches; 39,245 welding seams for a total of 72,206 weld inches; approx. 70 t of pipe supports) mostly made using C-steel and some VA, but also piping with PE cladding, fibrereinforced plastic piping, Victaulic piping and tubing – pressure testing of installed pipes using oil, water and air - installation of process equipment(522 t)
- material management, corrosion protection, non-destructive testing of welded seams
- 195,968 total working hours for piping installation: up to 270 technicians on site divided into different working groups
- implementation of tie-ins to existing pipe bridges/partial systems
- installation of 7.6 t as well as the supply, production and assembly of 11.4 t of small steel parts
- repair of fire-proof coating

Did we raise your interest?