The entire piping system for the new Moorburg power station (double block coal plant with a block output of 820 MW) in Hamburg was efficiently planned and constructed. IMO also acted as GMC for the primary water cooling system.
Scope of the work
- Engineering
- Fabrication, supply and assembly of
– approx. 970 t of pipes made from C-steel, stainless steel, fibre-reinforced
plastics and PE
– approx. 267 t of pipe supports
– low pressure piping for primary and secondary cooling water
– water and utility systems - Wall and ceiling bushings
- Labeling
- Fittings
- Insulation, scaffolding, transport, material management
- Quality assurance
- Commissioning, trial operation
- Documentation